Funding for the Met Branch Trail Should Be Restored in Montgomery County’s Budget

Yesterday, representatives of the Montgomery County Department of Transportation provided the County Council’s Transportation and Environment Committee with an update on its work on the Metropolitan Branch Trail. Work on the MBT been stalled for some time due to disputes over its crossing at Georgia Avenue and proposed routing that would have the trail pass by the historic Silver Spring train station. The train station is controlled by the nonprofit Montgomery Preservation Inc.
Despite
protestations on its website that MPI is not stalling the project, MCDOT’s update yesterday showed that MPI is in fact preventing the project’s moving forward. Delays are attributable to MPI’s unwillingness to accommodate the
master plan trail alignment, which led Montgomery County’s county executive to propose delaying the funding of the project for a year.
Fortunately, all three members of the T&E Committee—Roger Berliner, Nancy Floreen, and Hans Riemer—as well as Councilmember Valerie Ervin, who is not on T&E Committee but represents the District that houses the MBT and the train station, expressed strong support for the trail as well as frustration at MPI’s unwillingness to support proposed solutions.
Specifically, because the train station is historically designated, changes must be approved by the Maryland Historic Trust. However, only MPI—due to its control of the station–can make that submission and initiate the review. According to MCDOT, it refuses to do.
As a result, the county is being blocked from building a trail that will serve hundreds of thousands of regional residents, is included in the County master plan, and was previously supported by MPI.
During the hearing, councilmembers expressed frustration with the situation and asked the county attorney to review the situation. They hope that agreements with the county that have, over the years, given MPI control of the property and funding will provide a way to move forward.
This impasse is unfortunate, but we appreciate the strong showing of support from the T&E Committee and Councilmember Ervin. We firmly believe that the county should assert its rights and authority over the project and the process and continue to move forward with its design, which respects both the community’s need and demand for the trail and the historic significance of the train station.
MCDOT’s Edgar Gonzalez stated that the delays stemmed from past action and that within two months the county should be prepared to move forward, with or without Montgomery Preservation Inc. Therefore, this year’s delay in funding for the trail is unjustified.
For all the complexity of MPI’s involvement and the historic land use issues surrounding the Silver Spring train station, the County’s representatives are in agreement that it is time to move forward with the Met Branch Trail. MCDOT says it will have a way to do so within two months. Montgomery County should budget accordingly by restoring funding for the trail in this year’s budget.
Watch a video of the Transportation and Environment Committee discussing the MBT (the discussion runs from 12:25 to 33:00) here.